Bunker Update Week 5


Bunker Update Week 5

As we finish our 5th week of bunker reconstruction I am extremely happy with the progress we have made.  We have 16 bunkers that are completely finished!  Four more that only need sand added to complete the first set of holes.  This would include 6, 7, 8, 10, 11, 13 and the practice bunker.  The second phase is full steam ahead with 24 more bunkers under way.  As of the end of the day on Monday the 18th there are only 1 more of those bunkers to rough shape.  The crew has installed gravel and drainage in 6 bunkers so far and should be done sodding around the second phase this week.  Very exciting!!