Bunker Update Week 5
As we finish our 5th week of bunker
reconstruction I am extremely happy with the progress we have made. We have 16 bunkers that are completely
finished! Four more that only need sand
added to complete the first set of holes.
This would include 6, 7, 8, 10, 11, 13 and the practice bunker. The second phase is full steam ahead with 24
more bunkers under way. As of the end of
the day on Monday the 18th there are only 1 more of those bunkers to
rough shape. The crew has installed
gravel and drainage in 6 bunkers so far and should be done sodding around the
second phase this week. Very exciting!!