Friday, March 1, 2019

Bunker update week 3


Bunker update week 3

The weather has held off this week and we have gotten a ton done on the project!!  As of Thursday afternoon we have completely sodded around 5 bunkers.





We have 20 bunkers that are currently under construction.  All of them have been shaped and edged, and by the end of the week they should all have drainage and gravel in them.  Next week we will be sodding around the rest of those 20 bunkers.  We will also be spraying the Better Billy Bunker polymer on the first batch as well as starting to install the sand.  The construction will move toward 11 fairway and 15 greenside bunkers.