Bunker Update Week 4



Bunker Update Week 4

As we approach the end of the fourth week of the bunker renovation project bunkers are starting to be completed!  We started adding sand to the new bunkers on Thursday beginning with number 13.


By the end of the week all of the bunkers on 13 will be complete as well as a few others.





The new look is very exciting and will freshen up the look at James River moving forward toward our centennial celebration!  The membership is welcome to play out of the new bunkers, but please take a mandatory drop from the sodded areas.
We will be finished spraying the polymer in the first 20 bunkers this weekend, please stay out of any bunker that has a beware sign in front of it.  The polymer is very sticky and not good for you or your clothes until it dries, and we do not want to compromise the liner by disturbing it while it is curing.
The next phase of bunkers includes numbers 2, 12, and 14-16.  We will be removing the old material and shaping the next set of bunkers using the same procedure as phase 1.  Keep your fingers crossed for dry weather so we can stay on schedule!!