Double Eagle Construction started work on schedule earlier
this week. They have made good progress
rough grading the back nine and the practice green. The rough grading should be
complete this week.
The next step is fine grading and sodding which is done by a
different work crew. That work is
scheduled to start Monday and it should be finished in a week.
In the meantime, our staff began work on the front nine yesterday,
so we enter the period where both nines are closed. The large core aeration and top dressing will
take two days and that will be followed by the soil sterilization of the green
surrounds. Those areas will be covered
with tarps for four days. The tarps will
come off towards the end of next week, timed to occur as Double Eagle wraps up
the back nine.
We have been fortunate with the weather. Let’s hope it continues. Enjoy your opportunities
to play other courses. Call the golf shop for more details!
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEgHfxq5FVN2m7hddp_TCoiRsryC_cCW0i-rADb8kzcH4WEcm8tR9poeSySwz-RGIf8PQ-V8UkirEqskNkkWLjbx1Evto-1msEJ3PD2Am-5z61gxa-FeZLALSkiUBNX_YAUtoXathiWTkAeH/s1600/2014-09-30+13.13.37.jpg) |
Jeremy Franks with Mark Gooden |
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEgTtmiyVHMNhFO1sMNcyVRnvLy0WYnBSxwre_hqholRWDm8_qUzbzfPczAmkgpf7xEtzGzVCi_MjP5OdvRUXitZltQi-JmoZNivw6C62nKfGf86bVgsV5ZnuQPt7HASaaEfPHSgbH_b_GtY/s1600/2014-09-30+13.13.51.jpg) |
Rough grading |
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjn8QWNi7REZQqzTu02fMMhS0vOf9wzUCTHEGtaMEh7TYY0MTcvGsJqaRoSvZtMWGqr-SRiXAJZyFnvSpn0AEjeWNJyTWCEeQZzgQah9c0xK3tiA8-leWS6T0U4nDjEYjyvmZOwTpDoWo-T/s1600/2014-09-30+13.14.19.jpg) |
Rough grading with Jay Long |
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjc_lqhRTL3JUl4r1o6nYVnscJhsNMlThuJuONkJ3riUHl-255J9MoLFpg9WKSBqSd79SARHuagSUnFUB8K6o8PJUIYKXRaJLouWLLbAv_tCQ4kmzvWRLzHrgmUPOzwv8xsXJB5CopHg1JQ/s1600/2014-09-30+13.18.23.jpg) |
Discussing the finished product |
No comments:
Post a Comment