Bunker Project Week 1 Summary Feb 11-17.


Bunker Project Week 1 

Contractor worked 40 hours.
Only 4 days due to rain or wet conditions
Cleaned out 17 Bunkers.  All of 6, 7, 11, 13, practice bunker, green side on 8, fairway bunkers on 10.
Rough shaped 11 bunkers.  All of 7,11,13, Fairway bunkers on 10, practice bunker.
LaFoy will be here on Tuesday or Wednesday to approve shaping and place paint line for sand edge on shaped bunkers.
Rough Sod estimate on first 11 bunkers is 13,500 sq ft.
Once shaping is approved, we will begin edging and draining the bunkers.  Should happen this week.
We have taken delivery of 123 Tons of gravel so far.
Fill dirt at the shop has been excellent.  Area by old rain shelter did not yield good material.