Tuesday, February 26, 2019

Bunker project week 2 Feb 17-24


Bunker project week 2  
Feb 17-24


The second week of the project went well considering we were only able to work 4 days due to all the rain we had.  The Architect was out on Monday afternoon and approved 17 bunker for drainage.  He painted the lines to delineate where the sand will be and the crew dug out the edges to install drain pipe and gravel.  Two inches of gravel go in first then ultimately sod around the bunker and 5-6 inches of sand to bring the bottom of the bunker up to the edge line.  We got the drainage done on the left side bunker on 13 the second week.  To date we have cleaned out 19 bunkers, filled in one bunker and edged 5 bunkers.  The beginning of week three look like great weather, we should be able to drain many more bunkers and get in a truck of sod to tie in the edges.






Tuesday, February 19, 2019

Bunker Project Week 1 Summary Feb 11-17.


Bunker Project Week 1 

Contractor worked 40 hours.
Only 4 days due to rain or wet conditions
Cleaned out 17 Bunkers.  All of 6, 7, 11, 13, practice bunker, green side on 8, fairway bunkers on 10.
Rough shaped 11 bunkers.  All of 7,11,13, Fairway bunkers on 10, practice bunker.
LaFoy will be here on Tuesday or Wednesday to approve shaping and place paint line for sand edge on shaped bunkers.
Rough Sod estimate on first 11 bunkers is 13,500 sq ft.
Once shaping is approved, we will begin edging and draining the bunkers.  Should happen this week.
We have taken delivery of 123 Tons of gravel so far.
Fill dirt at the shop has been excellent.  Area by old rain shelter did not yield good material.

Tuesday, February 12, 2019

February 12, 2019 Bunker Project Video



February 12, 2019


The bunker project is officially underway, only one day behind schedule.  Rain kept us off the course on Monday, but Tuesday we got the crew started.  We started near the shop to facilitate less damage to the course while transporting material to the dumps site.  Sand, sod and old drain lines are being removed until it dries out enough to start hauling soil back in to shape the new edges.