Greens aeration went well this spring. We used pretty large tines and removed tons
of thatch and silty soil from the greens.
The process was aided by a box that attaches to the aerator pulling the
plugs into a pile at the edge of the green for clean-up. We used around 65 tons of sand to fill the
holes that we opened up by aerating. The
sand has a larger particle size to help with water infiltration on the
aging and heavily thatched greens.
Follow the maintenance staff as they continue to make improvements to the JRCC Golf Course
Tuesday, April 7, 2015
Spring Aeration
Friday, March 20, 2015
Aeration is coming
This week we finished up spraying the golf course for weeds and
applying the crabgrass preventer. All of the cart
paths have been edged and a good portion of the mulch is complete on the golf course.
We are now starting to prepare for aeration. We completed the process on the nursery green behind 13 and it went well. The process is aerating the green, removing the cores, applying sand, applying fertilizer and then brushing it all in the holes. Lastly, we will roll the green.
We will keep the mowers off of the greens for the first week. The following week we will start the mowing process and will keep at it until the greens are healed. They should be good after two weeks and great again after three, weather permitting.
Saturday, March 14, 2015
Spring is almost here
Spring has finally peeked its head out from under the snow blanket!
It is great to be out doing golf course work again.
We
have started mowing greens again on a regular basis with the walking greens
mowers and they are getting their color back after a brutally cold winter.
Nutrient applications are also being made to improve the soil chemistry
in the greens mix. This will allow the plants to better withstand stress. You
will notice fertilizer particles on the putting surfaces that can be a little
inconvenient at times, but they are essential to getting the greens ready for the
summer.
These nutrients will combat stress from traffic and heat to give
the turf the best chance for survival when the heat sets in. We are also
getting out the pre-emergent for summer weeds, crabgrass in particular.
We are spraying it on the bermuda areas along with a weed killer to clean
up the winter weeds. The fescue grass areas in the tree lines are being
fertilized with a product that also contains the pre-emergent.
Ball washer
restoration is almost complete and they should all re-installed by the beginning
of next week. Mulching and cleaning up the flower bed areas continue. The Clubhouse
and road areas are almost done, and then we will move to the golf course.
Time to get out there and play some golf!!
Friday, March 6, 2015
Welcome Rob Wilmans!
Here is an update from Rob after this first month with us.
I have been on property for just over a month now, and unfortunately have been under snow for over two weeks of it!
Prior to the snow the staff did a great job of getting the leaves
off the course and getting all of the
beds pruned and ready for mulch. The
clubhouse front entrance has already been mulched and looks great!
Since we have had a lot of time indoors, we have been working on improving the maintenance building. "Small" things like painting and adding blinds goes a long way! Along with that, we have been clearing out trash, organizing items, and purchasing any tools/ items we will need for this coming spring. The staff has also been refurbishing course accessories such as ball washers and benches.
Also new the James River staff is Ruby, my American Bulldog puppy. She will be assisting in goose abatement once she gets older. Last but not least, I want to thank the membership for trusting me with your course. I look forward to fantastic season!
Saturday, January 10, 2015
Winter Projects
As we prepare for the 2015 golf season, the maintenance department is busy finalizing leaf removal and finishing the drainage projects. Below are pictures of a French drain being dug on hole #7.
| Getting ready to lay drains |
| Markings on #9 for work to be done next |
You may also notice markings on #11 which is planned to be completed this month.
Saturday, December 13, 2014
Golf Course Winter Project Update
With the
decided shift in the weather, golf course maintenance activities have shifted
from cutting fairways to blowing leaves and cleaning up storm debris. The
biggest impediment to this process is wet weather. Since fairways do not dry as fast this time
of year, it is difficult to keep up with leaf removal. Everyone knows tractors
on the fairways are not a good thing, so we appreciate your patience. Feel free
to use the “leaf rule” to speed up play.
The
greens continue to grow over the winter and we are monitoring places on the
greens that have had damage prior to the project.
Some of these areas are being allowed to grow in and other areas have been
plugged. This healing process will
continue into the spring. You might
notice different mowing patterns on the greens.
Normally the operator mows in a straight line and goes off the green to
turn the mower. Because all the areas
off the greens had new Bermuda grass sod that required a lot of water, the operators
have mowed the greens in a circle (to stay on the green) rather than back and
forth.
This
mowing pattern has resulted in some scalping, which will heal. At this point the Bermuda grass has become dormant
and the green irrigation system has been turned off. As the surrounds dry out the operators will
return to normal mowing patterns.
On #4
you may notice some scalping which is due to the new surface not being
perfectly smooth. The USGA recommends beginning
mowing as soon as the turf is well rooted.
Quoting the USGA, “Since it is almost impossible to keep the green
surface perfectly smooth (due to the frequent irrigation necessary during
establishment) some scalping is inevitable.
However, it is better to scalp the new turfgrass plants early (and have
time to recover) than wait to lower the cut just prior to opening.”
The
final phase of the green renovation project was to inspect and replace the defective subsurface green drains.
Fortunately the drain problems we identified were in the main drain
lines off the putting surfaces, so we only had to dig up fairways and roughs.
Since the last update, the drainage work on holes 7, 9, 12, and 18 has been
completed. On the 7th hole,
we added a “smile drain” which is an arc – like a smile – that wraps the low
side of the green which will improve the bent grass on that part of the green.
Finally
the excess dirt we removed from around the greens has been placed in bare spots
around the golf course. It is being
tilled and seeded for the winter. As
stated in a previous update, play these areas as ground under repair.
Thursday, November 20, 2014
Golf Course Renovation Update
The
remaining areas of the course that had not opened after Double Eagle finished
their work are now open. This includes
the practice putting green, #4 green, and the front of #7 green. In addition,
the drain work on the front of #4 and #17, right of #13 and #3 have been
completed. The only remaining work items
are the drains on the front of #7, left of #9, left of #12, and left front of #18.
![]() |
| #7 After |
Keep in
mind that we are only talking about the subsurface drains that move water off
the greens. If the budget allows, we
plan to add fairway drains in the front of #1, #7 and other areas of the course
that do not drain well.
The new bent grass sod edge on all of our greens has done well. It loves the cooler temperatures and it
should continue to grow in on mild days when ground temperatures are
between 55° and 65° F.
The Bermuda grass
sod appears to be doing well, but it has largely gone dormant. The final verdict on the Bermuda grass will
come in the spring. If it attached properly, it will green up with the rest
of the golf course. We seem to have had enough nice weather this fall and we
are optimistic that the new Bermuda grass will thrive this summer.
![]() |
| Putting Green |
The
large tine aeration (5/8 inch) that we did at the beginning of the project is
slow to heal (if you look closely you can see where the aeration holes were),
but healing as planned. We will continue
next year with an aggressive aeration program, the schedule for which will be
determined by our golf course maintenance.
We will have additional testing done by ISTRC next year to make sure we
get proper water infiltration rates on the greens. According to the report done this summer, too
much water is being retained in the soil on our greens and we will continue
aggressive aeration until that condition is fixed. Their
report dated August 29, 2014 is posted on our web site for those who are
interested in reading. Click here to go to the website (the document is at the very bottom of the page).